Chiblow G.S. Turbine Gearbox Refurbishment
In this project Soo Foundry was responsible for the removal, rebuild and installation of a gearbox. We did a survey of the foundation and reworked
In this project Soo Foundry was responsible for the removal, rebuild and installation of a gearbox. We did a survey of the foundation and reworked
Our large capacity lathe lets us take on work that typically needs to be sent out of the region. This capacity combined with our ability
Our 70-ton crane capacity allows us to repair the 50-ton casting in a climate-controlled environment. We can manipulate the casting into a more welding-friendly position
This project consisted of adding PLC I/O drops, changing the existing AC motor/encoders to servo drives, migrating individual controls of each cut-off machine to a
SFM recently obtained their 47.2 /59.2 CWB aluminum certification. We have two qualified welding supervisors on staff, as well as three certified welders. We now