SFM provided shop fabrication and on-site installation of access platforms and ladders at a remote Northern Ontario hydro electric plant. Access to the work area was accomplished by using our engineered man basket on a mobile crane and utilizing a barge to stage tooling. All work, including inspection of the tailrace gates, was completed by working 12hr shifts for 21 days straight.